Speechly Bircham | Inform: Construction & Engineering

August 2008




Inform: Construction & Engineering

Speechly Bircham

Welcome to the second issue of Inform: Construction & Engineering


This bi-monthly newsletter aims to bring you up to date with recent developments in the Construction & Engineering world.

 

There is a focus at the moment within the Construction & Engineering industry on payment practices. With the Beijing Olympics underway we look at a change in the NEC suite of contracts, which have been selected to deliver the London Olympic projects. The new Option Clause affects project bank accounts and we take a look at how it works.
 
We also focus on the reform of the Construction Act which was published by the Government in a draft Bill, in part to outlaw some of the payment practices which were introduced to avoid the provisions of the original Act. Furthermore we look at a recent case which offers guidance to individuals selecting an adjudicator.

 

Andrew Steele

Partner, Construction & Engineering

  Top stories

Selecting the right adjudicator
We all like to have an advantage.  That is particularly the case where there is a dispute.  You would want your dispute decided by someone who is knowledgeable, suitable and available.  In arbitration that is not usually a problem because the parties have time to agree on the identity of their arbitrator.  In adjudication it is often different because the parties, once in a dispute, find it difficult to agree on anything and nominating bodies are usually quick to secure the appointment of an adjudicator. Read more.


Draft construction contracts bill: review of proposed amendments

The proposed changes to the Housing Grants, Construction and Regeneration Act (the Act) have now been published by the Government in a draft Bill.

 

The Act currently only applies to written contracts and the Bill will extend this to oral agreements. The Bill now omits the clause which requires the referring party to pay both parties' adjudication costs, irrespective of the outcome. The adjudicator is also now entitled to review the reasonableness of any allocated costs.

 

Furthermore the Bill targets the impact of contracts concerning payments to suppliers. The Bill prohibits 'pay when certified' provisions (ie provisions which make payments dependant upon the issue of a certificate under a different contract).  In addition, the provisions regarding payment notices have been enhanced so that a supplier will now be entitled to issue a notice to the purchaser, detailing the amount they consider due and the grounds for that belief. However, the purchaser will still have the right to service a notice should the supplier fail to do so.

 

The suspension provisions have also been improved so that the supplier can cease part (but does not have to cease all) of the works if there is non-payment. If works then re-commence, the supplier will be entitled to its reasonable re-mobilisation costs.

 

Feedback on the draft Bill is due by 12 September and it will be interesting to see what that response is. Read more.

 



www.speechly.com
subscribe
forward this email
Contact us

Andrew Steele
+44 20 7427 6508

 

David Gwillim
+44 20 7427 6604

 



Other stories

 

New NEC3 option clause on project bank accounts

The NEC suite of contracts has been selected to deliver the London Olympic projects - One of the reasons for this is its emphasis on trust and collaboration. In the same spirit a new NEC document allows users to introduce fair payment practices such as project bank accounts, as recommended in a guide produced by the Office of Government Commerce (OGC). The Olympic Delivery Authority has previously indicated that project bank accounts may be used where appropriate. Read more.

 

Offers to settle - part 36

As of 6 April 2007, the court rules regarding offers to settle disputes changed very significantly.  CPR Part 36 sets out specific cost consequences for a party that rejects a settlement offer made by its opponent and then fails to achieve a result equal than or better than that offer at trial.  The principal change to part 36 was that a defendant was no longer required to make payment into court if it was to make an offer to settle a monetary claim.  Both claimants and defendants can now obtain costs protection by making a written offer of settlement in the form of a Part 36 offer.

 

However, although Part 36 seeks to impose some degree of certainty as to costs, costs are ultimately in the discretion of the court.   It is clear from the decision in Cava v BAA plc that the court can undertake a wide ranging review of all the facts and circumstances of the case in deciding whether the judgment was worth the fight and which party should get its costs.   In this case, the claimant beat the offer by the sum of £51.  Part 36.14 provides that where a claimant fails to obtain judgment more advantageous than a defendant's Part 36 offer, the defendant is entitled to its costs to the date of the relevant period expired plus interest on those costs, unless the Court considers it unjust. 

 

However, the Court of Appeal held that the new wording introduced a change of practice and the term "more advantageous" permitted a more wide ranging review of all the facts and circumstances of the case in deciding whether the judgment was worth the fight.  Here, the additional £51 gained by the claimant was more than off-set by the irrecoverable costs incurred in continuing to contest the case. The court considered that the stress of the litigation should be taken into account and that no reasonable litigant would have embarked upon the trial for only £51.  So, if judgement and the offer are at all close then given this judgment, a challenge regarding the costs consequences of Part 36.14 may well follow. 

 

For more information please contact Julia Strettell

 


Speechly Bircham LLP is a limited liability partnership registered in England and Wales (registered number OC321620) and is regulated by the Solicitors Regulation Authority. A list of members' names is open to inspection at our registered office, 6 New Street Square, London EC4A 3LX

 

This information is correct to the best of our knowledge and belief at the time of going to press. It is, however, written as a general guide, so we recommend that specific professional advice is sought before any action is taken.

Speechly Bircham LLP 6 New Street Square, London EC4A 3LX
Tel +44 (0)20 7427 6400 Fax +44 (0)20 7427 6600

 


To unsubscribe visit:
http://cecollect.com/vtu/7280586831987131aLC91


Concep | Our interactive email partner